Planned Improvements for Riverside Parkway & Loop 1:
The project will improve traffic flow while minimizing impacts during school hours and rush periods.
- Bid Amount: $1,588,988.60
-Estimated Budget: $1.7 million
-Start Date: 30–45 days after Notice to Proceed
-Construction Timeline: ~270 days
Northwest Georgia Paving (Calhoun) is the apparent low bidder for major intersection upgrades near AdventHealth Stadium. Four competitive bids were received from: Glosson Enterprises, C.W. Matthews Construction, JHC Corp. & Northwest Georgia Paving.
Our City Engineering Office, in partnership with EXP consultants and with support from GDOT, is reviewing all bids to finalize the contract.
Stay tuned for updates as we move forward with this important infrastructure improvement!